Prater Birmingham Mock Up
Friday, 23 October 2009
Cladding rails installed
Tuesday, 20 October 2009
Steelwork finally up
Monday, 24 August 2009
Secondary steel layout
Friday, 14 August 2009
Steel is created in 3D model
The brief: design and build this in 10 weeks
First design meetings:
Friday 7th August at Bolton
Wednesday 12th August at Hoxton, London.